I remove the top cover and remove the rev 11.1 control board . The ribbon cable to the mainboard has one wire disconnected in the picture .
The picture show how I test the mosboard and FETs . The mulimeter is in Diode mode . The first leg is always 1 . The third leg is between 450 to 650 . The mosboard in my 9000 kw have all green LED light on . The mainboard is good and worth 200 dollars . I will test the control board later .
Looks good. What transformer is in it? Four caps on the main board?
Looks good. What transformer is in it? Four caps on the main board?
The main board has 4 capacitors . The 9kw inverter is not connected to battery yet and the ribbon cable in the picture has a wire out which show the worker who get pay in peanuts do not care . The transformer is ASL6.5 which normally in a 15kw inverter . I have to test the rev 11.1 control board and check all wires and AC output board later with pictures . A bad LF driver or control board will destroy the good 200 dollars main board and all the FETs .
Looks good. What transformer is in it? Four caps on the main board?
This may be a good deal for you.
which show the worker who get pay in peanuts do not care
If you're so worried about the workers, why do you keep buying the product?
If you're so worried about the workers, why do you keep buying the product?
The product from Powerjack like inverter and cable and mosfets and main board are cheap . I am worried about the quality control which is almost none and I have to check every wires and mosfets and resistors on mosboard and burn spots on control board and LF driver and every screws on wires before power on with the inverter switch . IF the GS 12kw is assemble in China and all are 48 vdc and you do not have to open the box and check then I am worried as a buyer . I am stil checking my 9000 kw and will show what I find but so far it is worth 200 dollars and if working then worth 700 dollars .
5 minutes ago, dickson said:IF the GS 12kw is assemble in China and all are 48 vdc and you do not have to open the box and check then I am worried as a buyer .
That's never going to happen. Every single GS inverter shipped from China arrives in the States in a completely unusable state. Transformer not wired, without the WiFi board, and with zero programming in the processor. The factory can't even test that it runs before it goes out the door. All final assembly and testing is Sean's responsibility.
The pictures of the Main board for my test bench . The main board has no capacitor and only 4 mosfets . The purpose is to see if the rev 11.1 control board will blow up the 4 mosfets when the inverter power switch is turn on . IF the 4 mosfets blow up then it time to order a new rev 11.3 control board with LF driver . IF you have the rev 11.0 control board and blow up the 4 mosfets then you need to order new rev 11.3 mainboard to match a new rev 11.3 control board and LF driver and cost about 300 dollars .
That's never going to happen. Every single GS inverter shipped from China arrives in the States in a completely unusable state. Transformer not wired, without the WiFi board, and with zero programming in the processor. The factory can't even test that it runs before it goes out the door. All final assembly and testing is Sean's responsibility.
So nothing from China is tested before shipping?
So nothing from China is tested before shipping?
I am still testing my 9000 watts Powerjack and I can not trust the workers that JACK hire . I have not turn on the inverter switch yet . I found broken wires and broken connector . Later I will check the AC output board and look like it was miss wired . The GS 12kw can not be tested in China as Sean has to do the testing and final assembly .
Looks good. What transformer is in it?
Strange David is selling ASL 6.5 transformer again since Sean is selling transformers . I think the ASL 6.5 is the best transformer by Powerjack . Someone on this forum is using ASL 6.5 inverter 24/7 on his farm . I have to get my 9000 watt with the ASL 6.5 running but need more research .
<a href="/monthly_2022_12/1581392169_Screenshot(1169628).png.670fc6dcae8a5f7d1f2676bfed187ff3.png" class="ipsAttachLink ipsAttachLink_image" ><img data-fileid="1933" src="//forums.genetrysolar.com/applications/core/interface/js/spacer.png" data-src="/monthly_2022_12/555769005_Screenshot(1169628).thumb.png.ef9d889138af3155f1327254ea0b35df.png" data-ratio="56.2" width="1000" class="ipsImage ipsImage_thumbnailed" alt="Screenshot (1169628).png">
I have to get my 9000 watt with the ASL 6.5 running but need more research .
Did you test the control board?
Did you test the control board?
I connect the rev 11.1 control board to my test bench and the 4 mosfets did NOT blow up . The LF driver LED do NOT light up . Only 2 LED on the rev 11.1 control board light on steady with the test bench inverter power switch . The rev 11.0 has 3 LED on steady . The rev 10.3 has 4 LED on staedy . The new rev 11.3 control board test good but it has only 2 LED on steady . I do not want to blow up the good 24 mosfets in the 9000 kw Powerjack so I may use the new rev 11.3 control board . I like to know if anyone who has the rev 11.1 control board and how many LED is on steady .
Did you test the control board?
Would my December 2021 "8000" PJ AMG inverter have the latest board revisions? I need to open it up and look, I suppose?